Comstock Metals (NYSE: LODE) received a Written Determination from the Nevada Division of Environmental Protection (NDEP-BSMM) confirming eligibility for its industrial-scale solar panel recycling plant in Silver Springs, Nevada.
The project is designed to process more than 3 million solar panels annually, equating to approximately 100,000 tons per year.
Comstock has ordered all major equipment with deliveries anticipated by the end of 2025. Installation, testing, and commissioning of the facility are scheduled for the first quarter of 2026.
The company also expects to receive notification for an Air Quality permit in the next few weeks, following routine compliance and public notice requirements.
[translate:Comstock Metals (NYSE: LODE) ha ricevuto una Notifica di Autorizzazione Scritta dalla Nevada Division of Environmental Protection per il suo impianto di riciclo di pannelli solari su scala industriale a Silver Springs, NV, soggetto alle normali condizioni di conformità e ai periodi di pubblicazione.]
[translate:L'impianto è progettato per processare oltre 3 milioni di pannelli all'anno (fino a 100.000 tonnellate/anno). Comstock ha ordinato tutta l'attrezzatura con consegne previste entro la fine dell'anno e prevede l'installazione, i test e la messa in servizio nel primo trimestre del 2026.]
[translate:L'azienda si aspetta la notifica di un permesso di qualità dell'aria nelle prossime settimane.]
Comstock secures state eligibility for a large-scale solar recycling facility, with operations planned for early 2026 and permits progressing as scheduled.